c a
s e s t u d y : n u m b e r three
Second Severn Crossing
Invited by the client to take control of this section of a
project with only 6 weeks to completion was possibly our greatest
challenge in a network build that had seen us traverse the
UK in a double figure of eight from Lands End to Edinburgh
and back taking in London, Leicester, Leeds, Glasgow, Belfast,
Dublin, Manchester, Birmingham, Bristol and now a final link
to Cardiff.
The structure itself is quite amazing being 5km long and consisting
of 2 x 2km viaduct sections joined together by a 1 km suspended
central section. Each viaduct section comprising 2 parallel
and separate tunnel like chambers supported on columns from
the banks of the river. Each cross section being capable of
holding possibly 5 double decker buses, 3 upright and 2 laid
on top of those. Unfortunately the buses would need to be
dismantled down to less than 1.5m by 0.6m to get them inside,
this being the size of the only access to the viaducts, through
a single door at the land end of each viaduct. Access to the
central section was via the motorway hard shoulder and a lift
down to the walkway landing. In addition to this, such access
|
required
an escort and deliveries had to be made by the bridge maintenance
crews.
Task
To install a 144 fibre armoured cable through the structure
for the project completion date. Note;
nothing had been installed into this bridge since its construction.
In the project folder supplied by the client was a fax from
the contractor that purported to be the method statement for
the installation of the cable through the structure. It consisted
of 12 lines. When asked where the rest of it was, I was informed
by the contractor that that was it, he was duly informed that
he would be going nowhere near the bridge and that that section
of the project was being removed from his contract. In view
of the short timescale for this project I decided to invite
the bridge maintenance company to bid for the works, (who
better I thought to provide a method statement that would
satisfy them). The company declined for resource reasons (one
of which was to impact on our operation considerably) but
recommended a contractor that was familiar to them. Consequently
this contractor was invited to survey the structure and put
forward a bid. Whilst the method statement provided was reasonable,
the number of men employed (30) and the estimated time to
complete the works (9 weeks) reflected I believed a lack of
true understanding of the job, in so much that this ratio
calculated out at .5 metres of cable installed per hour, all
at a cost of some £264,000.00. I subsequently informed
our client that I was not prepared to allow this contractor
on the bridge either, at which point the client requested
that we undertake the work as principle contractor. Though
I found this to be rather unethical the client was insistent.
|