| |
c a s e s t u d y : n u
m b e r t w o
Bluewater Shopping Complex

The Task
Having won the contract to provide an internal GSM system
for One 2 One at the Bluewater Shopping Complex (some 17million
sq ft of shopping malls) our client was not able to design
a suitable fibre delivery system. With approximately 8 weeks
to opening Lythgoes were approached for assistance and the
existing design audited by our design team. From carrying
out the audit and studying the existing site drawings it was
obvious a site survey was required. A survey was undertaken,
and sufficient data gathered to start some preliminary design
work.
The survey revealed the difficulties in design being experienced
by our client. Faced with only 5dB of power, the designers
were struggling to keep connector losses within limits. It
became apparent the system could not be designed economically
using then available fibre termination equipment and an innovative
approach to the installation was required.
The Solution
Calling on our experience and innovative abilities, we were
able to design a system that not only
|
|
afforded total diversity and redundant capacity,
but also a system that reduced splicing and connectorisation
to a minimum. Working to a maximum power budget of only 3dB,
the design proved to be a complete success. The only splices
on the system are those to pigtails, and in view of the installation
time available, the design also kept the number of cables
installed to an absolute minimum, many antennas being served
from each of 3 terminal points on the ring feeder cable.
The client had specified that armoured cable be used throughout,
and in order to achieve the necessary bending radii, Pirelli
were called upon to manufacture a bespoke cable having 12
fibres per tube, thus reducing the bending radii to suit the
cable tray installation.
Suitable splice enclosures for the antenna locations were
designed in house by Lythgoes, and a terminal wall box that
would allow for ‘break-out’ splicing from the
feeder cable of only those fibres requiring termination at
that particular location was sourced.
Solutions now had to be found for delivering the armoured
cable to the roof of the complex and for fleeting the cable
along the cable trays.
Once all the information had been collated, the design was
finalised and submitted to the client. The design was approved
and Lythgoes were asked to submit a price for the installation
work.
Working with KJR Cables, an acceptable quotation was approved
and all materials ordered. A method statement and Health and
Safety file was prepared and accepted at first submission
by Bovis Lend Lease, the principal contractor for the site.
Installation began 20 days before the complex was to be opened
and work was completed on 3rd April, three days before the
official opening. |