| |
c a s e s t u d y : n u
m b e r one
River Sow in Stafford

As part of a larger scale fibre optic route that was project
managed by Lythgoes, fibre had to be installed between Tollgate
Industrial Estate to the centre of Stafford and all within
a limited time scale.
The options available were to:
- Install 2 x 110mm ducts via the public
highway through the busy town centre which would be
in excess of 11km of duct, approximate costs £1.8m
- Purchase sub-duct space in existing
duct route
- Install 2 x 110mm ducts partly along
public highway and along a public footpath following
the line of a disused railway (total length is 6.7km).
|
|
|
Whilst taking into account all the options,
the 3rd option was chosen, which was to install the ducts
partly along the public highway and along a public footpath
following the line of a disused railway.
The next stage was to determine ownership of the path and
whether the views of the third parties needed to be considered.
After pursuing the matter with both the Local Authority (L.A.)
and the Rail Property Division, a deed of sale was produced
to prove that the path was currently in ownership of the L.A.
However due to a section of the proposed route crossing a
designated SSSI (Site of Special Scientific Interest) and
because of the existence of badgers, discussions were also
held with English Nature. A wayleave was then successfully
negotiated and design work commenced.
The route between these two
sites involved the installation of a pipe bridge across the
River Sow in Stafford.
Along the route there were 10 structures most of which required
extraordinary works. The bridge over the River sow in particular
proved difficult to utilise within the structure itself. The
solution was to install a pipe bridge alongside the existing
structure by extending the piers.
This structure is maintained by the L.A. so any works adjacent
to these structures needed to meet with their approval. A
design was put forward to extend the existing piers and to
place a 250mm diameter plastic coated galvanised steel pipe
having a 10mm wall thickness on top. The pipe was assembled
at site and lifted into place by crane to sit in the pre-positioned
saddles.
The entire project was completed
without incident, in time and at a saving to our client of
approximately £1.24m.
|